Manufacturing · Operations · 2025
Eleven sites, one way of doing things
A components manufacturer running eleven plants on eleven processes, each defended vigorously by the person who designed it.
Client
Belmont Components
Practice
Operations
Duration
Nine months
Team
Five, two on site
The situation
Belmont had grown by acquisition. Eleven plants across four countries, nine of them bought rather than built, and every one still running the process it had on the day it was acquired.
Group finance could not compare them. Each site reported unit cost on a different basis, so the "most efficient" plant changed depending on who was preparing the numbers. Meanwhile the same component was being made three different ways, at costs that varied by 40%.
What made it hard
Not the process design. The obstacle was that each plant manager had spent a decade optimizing their own operation and was, locally, correct. Any centrally imposed standard would make at least four sites demonstrably worse, and those four managers knew it.
Standardization programs usually fail because the people being standardized are the only ones who understand what they will lose.
What we did instead
We did not design the standard. We ran a six-week exercise where the eleven plant managers designed it together, using a common cost baseline we built first so the argument had shared facts underneath it.
The baseline was the real work. Four weeks measuring the same eleven things across eleven sites, consistently, for the first time in the company's history. Once everyone could see the same numbers, three of the eleven processes turned out to be clearly better and the debate shifted from whose was best to how quickly the rest could adopt them.
Roll-out
We piloted at the second-worst performing site rather than the best, because a standard that only works where things already go well proves nothing. It took eleven weeks and was messier than planned.
The remaining nine sites went live over five months, and from the third onwards a Belmont plant manager led each roll-out rather than us.
Results
Measured twelve months after the last site went live
−22%
Unit cost across the network, against the shared baseline
0
Sites closed, and no plant manager left during the program
9 mo
From first measurement to final site live
The thing that worked was not being told what our process should be. Getting the eleven of us in a room with numbers we all believed was the whole engagement, really. The rest followed.